← Back

Requests

Title Type Project Status Contractor Submitted By
RFI-001 – Structural Column Spacing RFI Downtown Office Building Open Siemens Mike Anderson on 20 Jan 2026
DCR-014 – HVAC Routing Change DCR Riverside Apartments Pending Zublin Sarah Johnson on 19 Jan 2026
CR-007 – Window Specification Update CR Downtown Office Building Approved Goldbeck Bobby Wong on 17 Jan 2026
WR-023 – Waterproofing Membrane Repair WR Riverside Apartments In Progress Strabag John Smith on 16 Jan 2026
RFI-002 – Pile Foundation Depth Clarification RFI Central Plaza Tower Open Siemens Tom Jonas on 15 Jan 2026
DCR-015 – Stairwell Width Adjustment DCR Downtown Office Building Rejected Max Boegl Lisa Chen on 14 Jan 2026
CR-008 – Facade Material Substitution CR Central Plaza Tower Pending Goldbeck Mike Anderson on 13 Jan 2026
WR-024 – Drainage Blockage – North Zone WR Riverside Apartments Approved Strabag Sarah Johnson on 12 Jan 2026
RFI-003 – Beam Depth at Grid C4 RFI Downtown Office Building Open Siemens Bobby Wong on 11 Jan 2026
CR-009 – Door Hardware Substitution CR East Wing Renovation Pending Goldbeck John Smith on 10 Jan 2026
...